If I want to complete the sprint but some sub-tasks are not completed . 

How can I set it if I want to complete sprint and move the remaining sub-tasks which are not complete to next sprint?

Thank you 

 

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 18, 2024

Hello @Dr_Win_ST 

Subtask cannot be moved to and from Sprints separately from their parent issue. You must set the parent issue to a not-done status so that the parent issue will move to the next sprint do to being incomplete. It will take all it's subtasks to the next sprint with it.