If I want to complete the sprint but some sub-tasks are not completed .
How can I set it if I want to complete sprint and move the remaining sub-tasks which are not complete to next sprint?
Thank you
Hello @Dr_Win_ST
Subtask cannot be moved to and from Sprints separately from their parent issue. You must set the parent issue to a not-done status so that the parent issue will move to the next sprint do to being incomplete. It will take all it's subtasks to the next sprint with it.