Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,751
Community Members
 
Community Events
184
Community Groups

Can the Structure Gantt roll up the Gantt finish date based on a custom field

Can the structure Gantt use a custom field called "Code complete Target date" to roll up to an initiative's calculated Gantt Finish Date rather than the "end Date"?

1 answer

1 accepted

1 vote
Answer accepted
David Niro _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 11, 2023

Hello @Surekha Gupta ,

If "Code complete Target date" is a date field and you have Treat Parent Issues as Groups option enabled, this should work.

Hope this helps!

Best,
David

Thank you. Although it did not quite point me to the "manual scheduling configuration", the link you provided gave me a clue that I needed to configure the scheduling section. With this, I was able to make my Finish Date to align with my custom date.