Can I link sub-tasks when I create them?

Nick Menere Community Champion Oct 15, 2017

I want to create 3 sub-tasks - A, B & C so that A blocks B and B blocks C.

Am I able to do this?

1 answer

1 accepted

This widget could not be displayed.
Nick Menere Community Champion Oct 15, 2017

This can be done by linking the sub-tasks when they are created to the "Most recently created issue" (in this case, the previous sub-task).

Note. You need to use the full "Create issue" action to create sub-tasks so that you can edit other fields.

You rule will look something like:

Screen Shot 2017-10-16 at 2.21.01 pm.png

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

138 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you