Can I get a burndown / progress report of sub tasks within issues?

jmacfarlane
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2020

Can I get a burndown / progress report of sub tasks within issues?

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 27, 2020

Hello @jmacfarlane

Welcome to Atlassian Community!

Unfortunately, the Jira burndown report does not consider sub-task estimation, not counting it towards the completion of related Sprints. That being said, we understand the value of this functionality and created the following feature request to get it implemented:

Burndown chart doesn't take under consideration the sub-tasks estimation 

Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.

As a workaround, you can sum the estimation of your sub-tasks to its parent issue, using the burndown chart to display the parent estimation.

Let us know if you have any questions.

jmacfarlane
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 27, 2020

Excellent!