Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Can I archive or hide completed epics on the roadmap?

We are using the roadmap-view in a next-gen project to keep track of general progress on epics. As we move on, new epics are added while others become completed. Doing so, we run the risk of ending up with a huge list of mostly completed epics in a couple of months: we wan't to keep the roadmap view clean. 

Is there a way to archive or hide selected epics on the roadmap? Removing (deleting) them is not an option. 

5 answers

1 accepted

4 votes
Answer accepted

Posting this question, I was provided a suggested related topic that seems to answer this question. It looks like development on this issue is in progress at this time: 
https://jira.atlassian.com/browse/JSWCLOUD-17996

@Laurens Van Lieshout  is there any update on when this fix will be completed?

Like Mark Wickens likes this

is it still in development @Admin

I see this question repeated over and over, without any answers... Atlassian is awfully quite about it too...

2 votes
Eduardo Tolmasquim
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Oct 26, 2023

go to: Timeline > click: View settings > mark: Hide all completed Epic issues

I had the same issue, since closing the epics didn't remove them from our backlog.

But epics have their own "Marked as done" state (can't understand why), which you can set on the backlog.

  1. Navigate to your backlog.
  2. Select the Epic tab on the left.
  3. Select the dropdown arrow and choose "Mark as Done".
  4. Now the epic is done and does not appear on the roadmap.

@twb this was very useful thank you - I found that I also had to click on view settings (Top right of roadmap) and select hide all completed Epic issues - There is also an option for displaying epics that have been closed in the last x months

Michael Handa
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Oct 02, 2023

This is the answer.

I had the same issue, I solved it a minute ago.

  • created a classic software project and added the Beta roadmap
  • added an extra epicclosed status
  • updated my board filter with: ... AND status not in (epicclosed) ...
  • now I can put my epic in this new status and it dissappears from the board + roadmap
  • maybe this can be automated also but this is not needed for me