Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,552,624
Community Members
 
Community Events
184
Community Groups

Calculation of business day in intelligent value

Hey guys!

I'm doing an automation in jira where my goal is to send an email containing the review date of my project: last day of the sprint + 1 day, the next day being a business day.

I'm using the smart values ​​to help me so I tried: {{sprint.endDate.jiraDate.plusDays(1).toBusinessDay()}}

But to no avail, does anyone know how the smart value can be written?

Thanks!

1 answer

1 accepted

0 votes
Answer accepted

Hi Ana,

Something like this might work:

{{sprint.endDate.plusDays(1).toBusinessDay}}

Hope this helps!

This solution worked fine, thanks! @omcg 

Perfect, I'm glad this worked for you @Ana Luiza Chagas! Could you kindly mark the answer as an accepted solution?