Calculate time of story/task

Hello every one,

I don't know how use the time to describe my story and my subtasks.
I have 2 developers. My story have 2 subtask, a subtask for my developer 1 which is estimated at 3d and a subtask for my developer 2 which is estimated at 1d. My developer works in same taime so my story is estimated at 3d (the longer time, not the sum of each substask !)

How do you do it?

(Sorry for my poor english, I'm French...)

1 answer

By default, the parent task estimated hours will be the sum of all estimated hours for each sub task. When you log work against sub-tasks, your parent issue remaining estimate is automatically adjusted.

If this is not what you want, what do you want to accomplish?

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,308 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot