Burndown chart of EPICs/Stories expected to finish on particular date (Code Freeze)

Ashish Arora
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 3, 2025

I need help in a creating a burn down chart for a set of EPICs/Stories that are required to  finish at code freeze milestone. I do not want to use release burn down canned report from JIRA as it brings all stories and EPICs for other teams too. I need to only look at burndown chart sprint over sprint for set of stories that are planned for my project and are planned to finish by a certain code freeze date. This code freeze date is not in any JIRA field.

Can someone please help with that ?

 

1 answer

0 votes
Danut M _StonikByte_
Atlassian Partner
February 3, 2025

Hi @Ashish Arora,

Welcome to the Atlassian Community!

Unfortunately this is not possible with Jira's out-of-the-box tools.

A solution would be to search for a plugin on Atlassian Marketplace that offers such a gadget or report.

If you consider the option of using a plugin, our Great Gadgets app offers a Release Burndown Burnup Chart gadget that will fully address your need.   

If you configure this gadget with a filter/JQL that returns the issues from your epics and set the dates, you will get an epic burndown chart displayed on your dashboard.

This gadget is capable to make a forecast based on current velocity and can also display milestones.

image.png

See more details in this article: https://community.atlassian.com/t5/App-Central-articles/How-to-create-an-epic-burndown-or-burnup-chart-in-Jira-and/ba-p/2737935 

If you need any help with the set-up, feel free to contact our team at support@stonikbyte.com.

Danut.