Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,552,675
Community Members
 
Community Events
184
Community Groups

After Logging in the work, the Time Remaining does not get updated.

I have created a JIRA Task and the task has two sub-tasks. The developer estimated the effort required for the Task would be 2d 5h. 
The Two sub-tasks were created and an effort of 2d 5h was mentioned against the Task. The sprint was kick-started, and the developer was asked to log his efforts daily using the "Log work" feature on JIRA against the sub-tasks. 
The developer has logged in his efforts on the Sub-Tasks daily and at the end of the sprint, I find out that the "Time remaining" is not showing correct value at sub-task level and at the Task level. 
Have I done something wrong here? Please help. 
Thanks in advance!Jira_Capture.PNG 