Advanced Roadmaps: Sprint Capacity Rollup Intermittently Incorrect (doesn't match backlog view)

Shelley Wycoff
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2021

Our sprint total is 16.75 in the backlog (correct) but in advanced roadmaps the rollup says 18.8 (incorrect).  There are no filters applied and when adding the items included in the sprint you can see it also adds up to 16.75.  Why does the rollup show 18.8 (incorrect)?

2 answers

0 votes
Ricco
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 10, 2023

Advanced Roadmap is not rolling up based on Sprints, it's rolling up based on the Target Start and Target End Date, and as you can see your Epic MAV-3069 is rolled up to the same Sprint in terms of Target Dates, for that reason you got here 2 additional Story points and so it rounds up to 18.8 SP.

0 votes
Shelley Wycoff
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2021

Here you can see the issues in sprint 16 in advanced roadmaps saying it totals 18.8, but really the true total (backlog rollup) is correct at 16.75

JiraRollupIssueAdvancedRoadmapView.pngJiraRollupIssueBacklogView.png

Greg Borchers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 6, 2023

Any answer to this question? Question is old, but I saw the same problem today.

Suggest an answer

Log in or Sign up to answer