Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

2nd SCRUM Board in the same Project doesn't show the same Sprints

Hello,

I had 1 scrum board with current Sprint and 4 additional ones.

I created a second scrum board, in that new board, I see the current sprint and one more but not the last 3, so I created one that had the same name and date, but I can see that the Sprint number is different.

 

The second scrum board doesn't show all the epics, how can both board for the same project share the same sprints

Thank you

1 answer

1 accepted

1 vote
Answer accepted
Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 24, 2023

This is expected. Sprints that are created in one board will only be visible in other boards if those boards shows issues that have been linked to the sprints in the first board.

So in your example it means that on the second board you are seeing the current sprint and the other one because you have issues on that second board that is linked to those sprints.

Indeed, thank you so much! sorry for the delayed answered. I did add stories and the sprints appeared :)

Like Mikael Sandberg likes this