현재 저는 이슈유형에서 epic-task-subtask를 사용하고 있습니다. 

그런데 타임라인에는 epic-task만 노출되고 타임라인 화면에서 sub-task가 보여지지 않습니다. 3가지 유형 모두를 함께 볼 수 있는 방법은 없을까요? 또는 task와 sub-task 두 개의 유형 티켓을 동시에 볼 수 있는 방법을 알려주세요.

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 19, 2024

Hi @허가영(한샘몰PM1팀) and welcome to the Community!

If your question is about Jira Software, then I must share the sad news that showing sub-tasks on the (basic) timeline is not possible. There is a feature request that you can track here; JSWCLOUD-18677.

If you are on a premium plan, than you can use Plans (formerly known as Advanced Roadmaps), which does allow to display the full hierarchy, including sub-tasks.

Hope this helps! 