Stories in current sprint are not moving to the top of the backlog

I recently updated Jira from version 6.2 to version 7.5. Everything is working smoothly except for when I end a sprint. In the past, we would end a sprint and it would say the remaining stories are being moved to the top of the backlog. Now it is just saying that the remaining stories will be moved to the backlog and they are scattered all over the place. It was much easier before because we could just look at the number of stories left and drag the bar to include them in the next sprint. Now we have to go through and pick and choose each one. We found a work around by creating a new sprint prior to closing the current one. 

Is there a setting somewhere that can be changed to go back to the old functionality or is this just the way it works? Is there a reasoning behind creating a new sprint before closing the current one?

Thanks in advance!

1 comment

Warren Levy Community Champion Sep 28, 2017

Hi Dave

We're using the cloud-based version (i.e. latest) and have the same issue. As you've suggested, we also create a temporary sprint to hold the unfinished items from the closed sprint.

Comment

Log in or Sign up to comment
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

200 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you