Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,560,358
Community Members
 
Community Events
185
Community Groups

Stories in current sprint are not moving to the top of the backlog

I recently updated Jira from version 6.2 to version 7.5. Everything is working smoothly except for when I end a sprint. In the past, we would end a sprint and it would say the remaining stories are being moved to the top of the backlog. Now it is just saying that the remaining stories will be moved to the backlog and they are scattered all over the place. It was much easier before because we could just look at the number of stories left and drag the bar to include them in the next sprint. Now we have to go through and pick and choose each one. We found a work around by creating a new sprint prior to closing the current one. 

Is there a setting somewhere that can be changed to go back to the old functionality or is this just the way it works? Is there a reasoning behind creating a new sprint before closing the current one?

Thanks in advance!

1 comment

Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Sep 28, 2017

Hi Dave

We're using the cloud-based version (i.e. latest) and have the same issue. As you've suggested, we also create a temporary sprint to hold the unfinished items from the closed sprint.