Estimating Story Point

M_ Nurfajar Ridla April 11, 2019

I have a lot of sub-task which distributed on some user story. On every user story defined story point estimation. By the end of the sprint period, not all of sub task on user story fully completed, How Jira calculate burn out of story point which sub-task uncompleted?

For example :
As user i want be able to........ (21 story point)
1. sub task-1 (in progress)
2. sub task-2 (done)
3. sub task-3 (done)
4. sub task-4 (done)

 

How Jira calculate burn out point story with 1 sub-task uncompleted?

Than you 

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2019

It will burn down when what you committed to do (the story) is complete.  So there will be 0 burn down until then, at which time it will be 21.