You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
Hi,
I am unable to create a Task under Story. Only Subtask is possible but I have a need to have Story->Task->Subtask.
Please check/suggest
Regards
Asha
Welcome to the Atlassian Community!
Yes, this is correct, the hierarchy is Epic -> Story (or task, or any other name you want) -> Sub-task.
Sub-tasks of sub-tasks is an anti-pattern, it just makes a completely unusable mess in most cases. The best case is that it drags you into massive micro-management, which is completely unproduvtive.
You should be looking at your processes, trying to make them into a function shape that uses Epic -> Story -> Sub-task as intended. And probably look upwards above epic.
Hi Asha,
What kind of problem you are trying to solve? There must be another way to solve the situation.
Regards, Mindaugas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Asha,
That is not standard Agile practice and is not allowed in Jira.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.