Calculate due date based on Original Estimate

Liz T
Contributor
November 3, 2022

Use Case: We are using the Original estimate field to estimate how long a task should take. Ex: Original estimate = 3w

We'd like the End date to update when somebody updates the Start date on a task, based on the Original estimate.
Ex: Start date 11/3/2022 + Original estimate 3w = End date  (11/24/2022)

Question: Does anybody have a suggestion on how I could create this automation?
I got this far:
>>When field value changed --start date
>>then edit issue --due date
but then don't know what to put in...I've tried various JQL, but can't get it to work.

Would this need to be a JQL or should it actually be JSON?


4 answers

1 accepted

1 vote
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 21, 2013

You can use the jira.table.cols.subtasks advanced setting.

https://confluence.atlassian.com/display/JIRA/Configuring+JIRA+Options#ConfiguringJIRAOptions-advanced

See Advanced.

Markus Stoll
April 11, 2013

Dear Jobin,

as we have the same "problem" / demand on the resolution status in the subtasks overview list...

Is there any more detailed handling advice available on what exactly to add to which property file to make the "Resolution" visible in the list of subtasks? Following the documentation link above it is not clear to me which tweak would be required.

Thanks for your support and best regards,

Markus

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 11, 2013

Edit the property as mentioned above and add "resolution" at the end (of comma separated values).

Markus Stoll
April 11, 2013

Okay, thanks. I guess it becomes clearer know why I had the problem... Is it possible that this configuration setting is not visible for JIRA-OnDemand Administrators?

Markus Stoll
April 11, 2013

If this is our destiny... : -(

Thnx for your support and have a nice weekend!

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 11, 2013

You are right. This is restricted on onDemand. You won't be able to change it.

1 vote
Deleted user
March 26, 2014

Hi all, is this ever likely to be added in for OnDemand? Or has anyone found another way of achieving a similar outcome.

1 vote
Markus Stoll
April 11, 2013

Dear All,

as we have the same "problem" / demand on the resolution status in the subtasks overview list...

Is there any more detailed handling advice available on what exactly to add to which property file to make the "Resolution" visible in the list of subtasks? Following the documentation link above it is not clear to me which tweak would be required.

Thanks for your support and best regards,

Markus

Aspect Infra Team
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 11, 2013

Markus this is not an *answer* pls delete this post , especially after you add a comment with same content

0 votes
Jeroen
Contributor
November 20, 2013

That is a shame , I wanted to see the issuekey of the subtasks on the maintask

Suggest an answer

Log in or Sign up to answer