In Jira Cloud, can someone confirm if the following is correct please for Program Parents and Feature Epics:
When you create a Program Parent and then link Feature Epics underneath the Program Parent, the link type should be Child Issue?
When you create stories and link them underneath the Feature Epic, the link type should be Child Issue?
Thank you
Michelle Anderson
Hello, Good day. Please go to settings >> Issues >> Issue hierarchy. If you have the following hierarchy then your statement is correct.
Level 2 = Program
Level 1 = Epic
Level 0 = Story
Level -1 = Subtask
Thank you for you help Mohanraj, much appreciated.
Michelle