When I drag the duration of items in Jira Work Management Timeline, it changes these fields:
Is it possible to use a different date for the end date instead of due date? I want to use a "planned end date", which might differ from due date. I want to use due date for things that must be done by a particular time, e.g. things expiring, etc. Not all tasks/projects have due dates and I would drag forecasted timeframes as workloads change, but I don't want to lose that "due date" for the few things that have a hard deadline.