Does anyone know of a way to use the Yasoon outlook calendar feature that will show a roll up of all issues by due date, but NOT child issues/child issue due dates? I am using the 'Jira project issues' selection but it automatically includes issues and child issues, so the calendar view is totally crowded with items. 

1 answer

2 votes
Patrick Schüßler _yasoon_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 12, 2022

Hi @Brittany Melville 

Thanks for asking. I'm Patrick, partner manager at yasoon. 
In this case, I recommend using our "JQL issue" template and working with the filter "project = MUL AND issuetype NOT IN subtaskIssueTypes()". 
In this example, MUL is the project key, which has to be adjusted individually.

Let me know, if you have any further questions. 

Happy Monday and all the best, 
Patrick

Brittany Melville December 14, 2022

Hi Patrick, this is exactly what I needed. Thanks so much!