Closed sprints are not displaying in reburn down chart etc..) but displaying in issue search

Rami Reddy Oruganti November 28, 2022

I am using Jira cloud and facing below issue

when i click on complete sprint in sprint board it is closed properly but it is not showing in the burndown chart or any other sprint wise reports but when i click on issue search report all the stories are displaying

can you pls suggest how can i bring missing sprints into reports.

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 29, 2022

Welcome to the Atlassian Community!

When you say "closed properly", does that mean it was in the last column on the board when the sprint was closed?

Suggest an answer