Can we make the task cards (in software board) with no activity for a week highlighted?

Irena Klug
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 24, 2022

I a trying to find a way to highlight tasks on the Jira board that had not been touched for a week or so highlighted. 

1 answer

2 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 24, 2022

what type of project is this? If you have a full-featured board where you can edit the board settings you have a couple options:

  • add a Quick filter -updatedDate <= -7d
  • use card colors - you can add a card sidebar color to denote these using JQL - updatedDate <= -7d 
  • use a swimlane to separate these issues from the rest using the same JQL - updatedDate <= -7d  
Irena Klug
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 27, 2022

That's Brilliant, Thank you!

I have found a way to add a filter - but, where can I add card colours? 

 

Thank you,

Irena