Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Can we changed Jira Work Management Timeline settings?

Hi,

I have a couple of Jira Work Management projects and each of them have a different 'description' under timeline (improvement, bug etc) is there a way to change it?

Another question in documentation I can see hierarchical view as drop-down for task and sub-tasks but in my view I can only see task, subtask, bugs one under another without any parent-child indication.

Last one: what settings determinate issue type being created from timeline view?

 

Joanna

 

2 answers

2 accepted

1 vote
Answer accepted
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Aug 02, 2021

Hello @Joanna Bajda,

Thank you for reaching out to the Atlassian Community!

On the Timeline view, the first column will show the Issue type, Issue key, and the Summary, it’s not possible to change that. I’m not sure if that’s what you meant by the description, if not, please let us know more details.

Regarding the sub-tasks, if it’s added to the issue type scheme, it should show a + sign next to the ticket to create it.

Screen Shot 2021-08-02 at 15.49.56.png

Screen Shot 2021-08-02 at 15.50.09.png

To check the scheme, please go to Project settings > Issue types and confirm if the sub-task is listed there. If not, on this very same page, click on Actions > Edit issue types and drag and drop the sub-task from the right to the left column > Save.

Another thing to check is if the sub-tasks are enabled on your site, so go to the Cog icon > Issues > Sub-tasks and confirm if it’s enabled.

What settings determinate issue type being created from timeline view?

It’s the default issue type set on the issue type scheme. Project settings > Issue types > Actions > Edit issue types > Default Issue Type.

Screen Shot 2021-08-02 at 15.58.00.png

Kind regards,
Angélica

0 votes
Answer accepted
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Sep 20, 2021

Hi @Joanna Bajda  - Just checking in on this. Were you able to try some things? 

Hi,

yes it's working fine.

Like John Funk likes this