Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,557,130
Community Members
 
Community Events
184
Community Groups

how to maintain the Gap between the development Task Completed to QA Task Completed

Edited

In Jira software, I am unable to maintain the Gap between the development Task Completed to QA Task Completed

when the user story completed at that time this task will assign to the development team

the development team completed the task and assign it to the QA team 

then the Development team completed the task 

so in these cases how to maintain the Development Task Completed to Tester Task Completed Date 

1 answer

1 accepted

2 votes
Answer accepted
Magdalena Zhisheva
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Apr 07, 2023

Hi @Durga Solse , 

You can try to create an automation rule like for example, 

1. If a ticket is transitioned to "Test in progress" -> assign it to

2. If the ticket is moved to QA Complete -> assign it to 

The points above are just example and you can customize it.

 

As another scenario, you may put validators or conditions in some of the status transitions in the workflow.

Hope it helps!

hi @Magdalena Zhisheva 

have any SQL query 

Magdalena Zhisheva
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Apr 07, 2023

Hi @Durga Solse , 

Sorry I didn't get that - do you need any help do build up your rule with JQL query?

Magdalena Zhisheva
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Apr 07, 2023

well, @Durga Solse  you need to define the trigger and what do you want to filter with that JQL filter.

Actually, the transition action do not require JQL query, you just need to define which status to trigger the check, so the action to be done.

Screenshot 2023-04-07 at 12.07.23.png

@Magdalena Zhisheva 

Thanks 

will check once 