Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

burndown chart with remaining hours not story points

what field is required (from the drop down) to trigger the burndown for remaining hours? 

I have searched and can't figure it out....yes sure story points (SP) shows but that doesn't help bc SP are only closed once the epics are done.

 

Thank you

4 answers

How does burndown with Original estimate makes sense. It should be with remaining hrs. That is the basic functionality anyone would as for a sprint tracking. I don't know how Jira could miss it.

Showing a burn down in story points is not useful for managing development.

The link provided above says that the time based burn down shows the original estimate less the time used.  This idea is from the 1900's - it is the equivalent to determining how close your are getting to your office in your morning commute based on the number of minutes you have been driving instead of based on your actual location and remaining distance to the office.

 

I need to be able to estimate in story points and have a burn down chart that shows  REMAINING TIME.

Did you figure this out?  If so, please let me know how.  Thanks

 

You have to go into your board settings and then under "Estimation" there is an option to select "Original Time Estimate" instead of "Story Points"

The field required should be "Remaining" not "Original".   

The "Original" value should not change, as it's the team's estimate.

When hours are logged, the "Remaining" value is reduced, not "Original" (which is correct) so a burn down for "Remaining" is required.

 

This article explains how to do it:

https://support.atlassian.com/jira-software-cloud/docs/configure-estimation-and-tracking/

I think this answer misses the point.  He wants to size in point, and show the burn down using hours.  That is what I want too. 

Like # people like this
0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jan 07, 2019

Hello,

Welcome to Atlassian Community!

You must be estimating your stories with time tracking fields instead of Story points to display the information in the Burndown Chart.

The field that should be selected to change the burndown Chart to display hours instead of Story Points is the Original Time Estimate:

Screen Shot 2019-01-07 at 19.01.24.png

If it's not properly appearing to you, you must activate the Time Tracking feature for your site and configure the field for your Stories, as described in the documentation below:

Configuring Time Tracking

Let me know if this information helps.

Actually I got a similar issue, at this moment I can't track "Remaining Time" on Burndown chart.

Deleted user Apr 14, 2020

I also turned on everything and this option is still not available. How come no one at Atlassian has learned that hiding options/actions (unless it is critical to keep it a secret) is the worst possible user experience?