Hi, I have created a jira put automation task and I want to date in summary the same day the request is created.

That is to say, if I have an automated request that is created every 7 days and specifically it is created on Monday 27/03/2024 I want the following to appear in the summary of the request: Request test 27/03/2024 and the date to be automatic.

1 answer

1 accepted

0 votes
Answer accepted
Sebastian Krzewiński
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 27, 2024

Hi @Jesús Lapido 

 

You can use for that automation and smart values.

Rule should look like below:

- Trigger: Issue created

- Action: Edit issue - choose summary field

- as a value please use {{issue.summary}} {{now.jiraDate}}

 

Hope that this will help you.


Regards,

Seba