I'm trying to look at a schedule for a ticket blocked by another.
Ticket A start 4/1-4/7
Ticket B blocked by A start 4/7-4/10.
If I move Ticket A on the portfolio/roadmap/planner view, it does NOT move Ticket B's start or stop dates. Should it do so? Should I get a warning?
Note: The dependency view works fine and shows the link but seems odd that in the schedule view it doesn't really do much at flagging dependencies.