Why does the sprint burndown gadget display remaining time estimate instead of story points?

Arturo Jimenez May 24, 2022

Hi all,

 

I would like to measure predictability using story points and show the burndown in a dashboard, but the sprint burndown gadget shows me remain time estimate. DO you know why? 

 

Wr2sKxzkcC.png

The user story has Story Points. 

 

o472dyGQlt.png

 

Thank you in advance 

1 answer

0 votes
Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 24, 2022

The reason the burndown chart is showing Time is because your board is configured to time as the estimation or the "Remaining Estimate and Time Spent" is selected. You can change that by going to Board settings > Estimation and change it.