Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Deleted user
0 / 0 points
Next:
badges earned

Your Points Tracker
Challenges
Leaderboard
  • Global
  • Feed

Badge for your thoughts?

You're enrolled in our new beta rewards program. Join our group to get the inside scoop and share your feedback.

Join group
Recognition
Give the gift of kudos
You have 0 kudos available to give
Who do you want to recognize?
Why do you want to recognize them?
Kudos
Great job appreciating your peers!
Check back soon to give more kudos.

Past Kudos Given
No kudos given
You haven't given any kudos yet. Share the love above and you'll see it here.

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

When will `Show capacity on timeline` be available for Advanced Roadmaps Jira Cloud?

Hello,

How Atlassian Uses Advanced Roadmaps <--- I was watching this video and was wondering... is capacity planning available for Jira Cloud?

Displaying capacity in a plan <--- The documentation here is for data centers and server.

The team capacity planner looks very helpful and I would love to implement it for our teams.

Thank you!

2 answers

1 accepted

1 vote
Answer accepted

Hi @Peter Yoon,

Capacity planning for Advanced Roadmaps is also available on Cloud, you access it by using the view settings menu to group by either Team or Sprint and then there is a checkbox "Show capacity on the timeline" that you can enable.

However - I notice that your question is tagged to indicate that you're on the standard plan, worth bearing in mind that Advanced Roadmaps is only available on Jira Premium.

Regards,

Dave 

Hi @Dave

For some reason it shows above that I'm on the Standard Plan. I'm on the Premium Plan and have access to Advanced Roadmaps.

Screen Shot 2021-05-10 at 5.59.23 PM.png

I see! I found the checkbox for `Show capacity on timeline.`

Screen Shot 2021-05-10 at 6.00.04 PM.png

Thank you!

Like Dave likes this
0 votes
Dave Atlassian Team May 10, 2021

It looks like you haven't assigned any of the issues to any teams. You'll need to make sure that you've created teams (from the "Teams" tab) and then associate each team with a board that sprints. It's worth noting that you need to use boards as issues sources for your plan (as this is where sprints come from). You then need to assign issues to specific teams.

Regards,

Dave  

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS
Community showcase
Published in Jira Service Management

JSM June Challenge #2: Share how your business teams became ITSM rockstars

For JSM June Challenge #2, share how your non-technical teams like HR, legal, marketing, finance, and beyond started using Jira Service Management! Tell us: Did they ask to start using it or...

320 views 9 7
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you