Velocity chart doesn't show data in hour estimation

Hi everyone!

My Velocity Chart doesn't show any information about my sprints.

I like to use only hours to estimate my stories and subtasks.

My board has this configuration (below):

My burndown chart works perfectly.

But my Velocity chart don't.

I was expecting that it showed my sprints' velocity in hours. But it doesn't show nothing.

Can anyone help me ?

Thanks.

Bye.

4 answers

Velocity chart will not be based on hour. Velocity chart shows how much work was commited and completed at the end of the sprint. Storypoint is most common measure of the amount of work completed in agile.

You can always estimate each stories in story point before the start of the sprint and continue taime tracking in hours during sprint. This will allow you to see a burndown in hours and velocity in story points.

The Velocity chart will show hours, but the catch is that it only shows hours for completed issues. So, if you've completed 90 out of 100 hours for an issue it will show as 0 for completion. Additionally, completion is based on the statuses that you've mapped to the Done column in the sprint configuration.

Does anyone know a way to get a Version of this report that shows actual hours completed (including hours burned down on issues that were not completed) I realize this is not "pure scrum" but it is the way my team likes to measure work completed in a task. We can't be the only ones - is there a plug in out there already?

Very weird because I have completed a lot of issues in each sprint.

This is my collumn configuration :

This is a completed story from a past sprint. We can see the logged hours and other informations.

I still dont understand why it doesn't show like yours.

Some idea or tip configuration to check?

Thanks!

Not sure, but you can check the sprint report to see what was calculated for inclusion and then see what issues you had.

Weird...

On Sprint Report, it shows "Original Time Estimate (0)"


But I dont know why it's showing zero hour(s).

I will tell you how I create/start my sprints:

1) We create a lots of story issues

2) We select some stories to sprint

3) We create a new sprint and set some stories into it

4) We create sub-tasks into each story and for each sub-task we set a estimated work in hours.

5) We have all stories planned with their sub-tasks and these sub-tasks have working remaing planned in hours.

6) We start the sprint.

So... that's it...

I did this since the beginning and I have never had problems... only with this Velocity chart.

Am I doing something wrong?

Thanks

Bye

Are you setting estimates at the story level or only on the subtasks? The velocity chart does not consider subtasks.

so that's it :(

I only set hours for the sub-tasks... and then I consider that the story estimative is the sum of all sub-tasks...

But... Is this wrong ?

No its not wrong, we do a similar thing per team. If only there was a few settings on these charts and we'd all be happier.

Frederico, it's been a while since you posted this, so you probably found the issue or are not interested anymore. Anyway, I think the problem you have (same I have) is that you are using sub-tasks. 

 

I think JIRA calculates Velocity using the time (only) from the story, but not aggregating time estimates from sub-tasks. There is a big discussion around JIRA community on when Atlassian will start calculating story time estimates adding the sub-tasks estimates: https://jira.atlassian.com/browse/GHS-9167

 

Hope this helps to everyone stuck with the same problem. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

17,622 views 18 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you