Velocity Chart is not showing our Committed Points

Rose Seed
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 26, 2024

We just started a new sprint and when I looked at the velocity chart it shows 0 committed points in the last sprint (37) and one previous sprint (34).  Not sure what is going on here. But we would like to have an accurate representation to review. Screenshot 2024-04-26 at 2.45.27 PM.png

1 answer

1 vote
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 26, 2024

Hi @Rose Seed -- Welcome to the Atlassian Community!

One possible cause of that symptom is the sprint started before the story points were set for the issues in the sprint. 

Did you check if that happened?  It is easy to see if you look at the burn charts as they will show the increase in scope (i.e., total story points) after sprint start.

Kind regards,
Bill

Suggest an answer

Log in or Sign up to answer