You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Good Morning,
My Velocity Chart doesn´t show all sprints, for example, sprint 7 is not shown and also the sprints are not in the correct order.
I´m the project admin but I´ve tried to disable “Hide unrelated sprints” viewing option from the Velocity Chart, but that option is not there :-)
Does anyone know why some Sprints may not show up and how to fix the Order of Sprints in the Velocity Chart?
Hello @Fernando_Reich
Welcome to the Atlassian community!
Velocity Charts will not show "all" sprints. They show only the last 7 sprints completed by the team. I have not played with this report much, but I would assume the selection of sprints and the ordering of them would be based on the Completion Date of the sprints that were created in the board where the report is being generated.
The "Hide Unrelated Sprints" option is available only in Jira Server/Data Center, not in Jira Cloud.
More information about the Velocity Chart can be found here:
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/