Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Upon logging effort, the burndown chart does not reflect it

We use days to estimate every ticket in a sprint. If a ticket has an estimate of 2 days, If the developer logs 1 day, I would like to see the sprint burn down chart to reflect the effort. How can this be made possible?

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Nov 14, 2023

Hello @K C Siddharth 

Are you working with a Team Managed project or a Company Managed project?

What have you selected for your Estimation statistic for the board?

In the Estimation setting do you have the Time tracking option selected?

Hi @Trudy Claspill ,

 

I work on a team managed project.

I use time as an estimation right now and not story points. Although we are planning to move to story points.

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Nov 16, 2023

When Time is your metric, the burndown chart is only able to show the Original Estimate time. The Original Estimate value does not itself change as you log work against an issue, so there is no change to show in that value on the chart.

Logging Work only updates the Remaining Time Estimate. The burndown chart is not capable of showing the Remaining Time Estimate currently, so it can't show the change in that value as you log work.

With a Team Managed project the Sprint Burndown shows the burndown only when the issue is moved to the column farthest to the right on your board.

Thanks @Trudy Claspill . This is quite helpful. Will make changes accordingly to reflect progress.