Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Unable to see the completed green bar in my velocity chart

Shreyas Shenoy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Oct 10, 2023

Hi Guys. I am unable to see the green bar of the completed section of my velocity chart. Please note it is not measured in story points here because I prefer to do it in hours. The chart is in original estimate hours versus sprint numbers. Ideally it should calculate as completed if the task is done. But something is wrong here. Please advise.

Note: I can see the committment part (Grey colour bar) of the chart.

2 answers

0 votes
Danut M [StonikByte]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Oct 11, 2023

Hi @Shreyas Shenoy,

Try also the Team Velocity gadget offered by our Great Gadgets app. It work differently than Jira reports.

It supports many estimation types, including time estimates, is more advanced than the Jira report and offers many other details.

Team Velocity Gadget 

Similar to this, you can display Sprint Burndown and Release Burndown chart by time estimates. See this article on our blog for how to do it: Tracking an agile project that uses time estimates with Great Gadgets for Jira 

The app offers many other gadgets that you will find useful. It can be a great asset for your team or company.

Hope this helps.

Thank you,

Danut Manda

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 10, 2023

Hello @Shreyas Shenoy 

Welcome to the Atlassian community.

As per the documentation for the Velocity chart

 

Completed: The green bar in each sprint shows the total completed estimates when the sprint ends. Any scope changes made after the sprint started are included in this total.

In a scrum board an issue is considered "completed" at the end of the sprint only if the issue is in the column farthest to the right on the board, regardless of the issue status.

Are you "done tasks" in the column farthest to the right on your board when you complete the sprint?

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events