Hi everyone,
Not sure if this is possible but Im trying to create an automation that fills in time spent in a subtasks with it's original estimate (or the time remaining) when task is moved to done.
Currently I have this automation set up:
The problem is that it takes the original estimate from the story not the subtask. So for example if the original estimate is 1 hour for the subtasks but 10 hours in the story then it will show 1 day and 2 hours time spent instead of 1 hour.
Does anyone know if there's something I can do to solve this?
However, keep in mind that log work will be made from "Automation for Jira" actor.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm glad that it worked! Kindly mark my answer as accepted, in order to help others who have a similar question to yours :)
Cheers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Alex Koxaras _Relational_ ,
I am trying something similar with little change. We do not use sub-tasks instead link tasks to story. Example below:
My team puts in the estimates and time spent against each task. While nothing is logged on story level.
But If I want to view the total of 'time spent' for task 1, 2 & 3 on story 1. How can I do that ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Chirag I would suggest that you create a new question on the community about this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.