Sub Task created from Task showing as Not Linked to an EPIC

Julie Mullen April 12, 2023

I have created a task and linked to one of my EPICS.  I then created 4 subtasks on the Task.  2 of these have successfully showing under the EPIC however 2 are showing as no EPIC.

Below is the issue which has been linked to an EPIC.  However on my Kanban board Sub Tasks 190 and 191 are showing as not Linked to EPIC

Issue linked to Epic.PNG Any thoughts?

Sub Task not Linked.PNG

1 answer

1 accepted

4 votes
Answer accepted
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 12, 2023

Hi @Julie Mullen and welcome to the community

I've managed to reproduce your issue, and this happens because your two subtasks (which appear to have no epic) are moved to another status while your Epic stayed in the backlog. Thus, no epic is visible on the kanban board. As soon as you move your epic on the kanban board (e.g. selected for dev) then these subtasks will move to a dedicated swimlane.

Julie Mullen April 12, 2023

Perfect - thank you very much