Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,555,496
Community Members
 
Community Events
184
Community Groups

Sub Task created from Task showing as Not Linked to an EPIC

I have created a task and linked to one of my EPICS.  I then created 4 subtasks on the Task.  2 of these have successfully showing under the EPIC however 2 are showing as no EPIC.

Below is the issue which has been linked to an EPIC.  However on my Kanban board Sub Tasks 190 and 191 are showing as not Linked to EPIC

Issue linked to Epic.PNG Any thoughts?

Sub Task not Linked.PNG

1 answer

1 accepted

4 votes
Answer accepted
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Apr 12, 2023

Hi @Julie Mullen and welcome to the community

I've managed to reproduce your issue, and this happens because your two subtasks (which appear to have no epic) are moved to another status while your Epic stayed in the backlog. Thus, no epic is visible on the kanban board. As soon as you move your epic on the kanban board (e.g. selected for dev) then these subtasks will move to a dedicated swimlane.

Perfect - thank you very much