Stories do not roll up due dates to Epic in Advanced roadmaps

Eirik Aune April 26, 2023

I am using advanced roadmaps to try to help my leadership understand what is happening.  However, the Epics are not rolling up the dates of its children.  My preference would be to have it infer dates from sprints, but even when the user stories have dates assigned it still does not roll up.

 

image.pngimage.png

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 27, 2023

Hello @Eirik Aune 

Take a look at this document and let us know if it answers your question.

https://support.atlassian.com/jira-software-cloud/docs/how-advanced-roadmaps-rolls-up-dates/

Also make sure you have the Roll-up Dates option selected in your View Settings.

Screen Shot 2023-04-27 at 3.54.30 PM.png

Eirik Aune May 1, 2023

Trudy, I had found the link but I had not found the magic checkbox!  That got it.  Thank you!

Like Trudy Claspill likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events