You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I am using advanced roadmaps to try to help my leadership understand what is happening. However, the Epics are not rolling up the dates of its children. My preference would be to have it infer dates from sprints, but even when the user stories have dates assigned it still does not roll up.
Hello @Eirik Aune
Take a look at this document and let us know if it answers your question.
https://support.atlassian.com/jira-software-cloud/docs/how-advanced-roadmaps-rolls-up-dates/
Also make sure you have the Roll-up Dates option selected in your View Settings.
Trudy, I had found the link but I had not found the magic checkbox! That got it. Thank you!