We're using the Sprint Capacity Planning & Tracking add-on by Addon Experts Center.
Seems like when you click the Start Sprint button in the Jira software on a day after the sprint start day, the add-on changes the number of days in the sprint and then recalculates everyone's capacity. Zat true?
We have our sprint planning meetings on day 1 of the sprint. Typically we keep making estimate adjustments and adding/removing issues to/from the sprint for the rest of the day and into day 2 of the sprint.
Then when I click Start Sprint on day 2 or even day 3 of the sprint, the bar charts all change so that we're all over 100%, and it seems as if the reason is that the # of days in the sprint was recalculated to be fewer. Is this what's happening? If so, it's undesirable behavior. Should leave the # of days alone.
To properly use this add-on, must I always click Start Sprint on day 1 of the sprint to avoid this? Thanks.
Catch up with Atlassian Product Managers in our 2020 Demo Den round-up! From Advanced Roadmaps to Code in Jira to Next-Gen Workflows, check out the videos below to help up-level your work in the new ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events