Hello Community,
I added all the stories to my sprint and started the sprint with a planned start time later in the day (planned - 23/Mar/23 4:00 PM) but still if certain stories were added/removed from the sprint they were reflecting as spikes/drops in the sprint report even before the planned start time (planned - 23/Mar/23 4:00 PM) which was set on the sprint. How can i avoid this and is this standard behavior ? Or should I start my sprint only after all additions/deletions in terms of stories are done. Or does it work differently for JIRA server and cloud versions ?
Regards,
Jai
Hi @Jai Ganwani , yes this is expected behavior. Even though the start date is in the future, once you lock in the sprint using Start then the content is 'locked'.
Hi @Jack Brickey ! I think i have done the same thing on JIRA server edition and it used to work differently if I remember correctly. All changes made to the sprint before the planned start time were not reflected as spikes/drops on the sprint report as long as it was done before the planned start date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.