You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I'm using an automation rule to set Original estimate to an issue. However, when I do so the Time remaining doesn't update. When I add Original estimate manually on creation, the Time remaining updates.
Does anyone know how I can solve this?
Found the answer myself, that for some reason I didn't see yesterday :)
The answer is to set both Original Estimate and Remaining Estimate in the Automation rule.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.