Removing Story from Sprint

If we have set a sprint and then based on planning and issues that came up I want to pull stories out of the sprint and back into the Plan (product) backlog to be picked up at a different time, how do I do that?

2 answers

1 accepted

To remove from a sprint, click on the issue key in the plan or work board so that the detail pane pops up. On the detail pane, click the cog wheel on the right and choose "Remove from Sprint."

Have you tried upgrading?

The ability to add issues to a running Sprint from the Plan mode was added in version 5.9.1 of GreenHopper

https://confluence.atlassian.com/display/GH/Adding+an+Issue+to+a+Sprint

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

751 views 5 17
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot