Removing Story from Sprint

Elizabeth Spilman April 2, 2012

If we have set a sprint and then based on planning and issues that came up I want to pull stories out of the sprint and back into the Plan (product) backlog to be picked up at a different time, how do I do that?

2 answers

1 accepted

0 votes
Answer accepted
Kim Wall November 26, 2012

To remove from a sprint, click on the issue key in the plan or work board so that the detail pane pops up. On the detail pane, click the cog wheel on the right and choose "Remove from Sprint."

0 votes
boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 26, 2012

Have you tried upgrading?

The ability to add issues to a running Sprint from the Plan mode was added in version 5.9.1 of GreenHopper

https://confluence.atlassian.com/display/GH/Adding+an+Issue+to+a+Sprint