Regarding Test Set Cascade and it's reporting in Jira server

jui kulkarni June 18, 2021

Scenario:
Lead engineer will cascade the the test set. Tester will include the the test set into different test plans and test executions and will execute the tests.
Lead engineer would like to see the status of the cascaded tests on dashboards at any point of time for different environments / gateways etc.
Can we achieve it using OOTB Jira XRay features and reporting tools?
If not, is there any add on available?

1 answer

0 votes
Rogério Paiva - Xray Xporter
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 25, 2021

Hi @jui kulkarni 

It depends on the way you have the cascade of tests organized in your projects.

Depending on the specific details of how you have it organized it might be possible to use the Test List gadget or not.

Please check the documentation here (https://docs.getxray.app/display/XRAY/Tests+List+Gadget).

Nevertheless, if it is not possible with the gadget, it should be possible with the Document Generator feature, since it is based on configurable templates, that can be coded as needed.

(https://docs.getxray.app/display/XRAY/Document+Generator)

If you need additional help, please contact Xray Support (http://xraysupport.xpand-it.com ) to request additional information and help further.

Thank you.

Kind regards,
Rogério Paiva [Xray Support Team]