We are using recurring tasks for jira core and have noticed if the task already scheduled is not marked done, a new task for the next scheduled date is not created.
Will the task generate once the previous task is marked as done?
Any guidance is appreciated.
Thank you
Hi @LisaF ,
If you don't manage to get any reply on this in here, I'd advise to contact the vendor by using the resources listed in the support tab of the marketplace page of Recurring Tasks for Jira Cloud:
Cheers,
Dario
Thanks Dario, we tested a few and worked out:
A new task does create even though the prior task is still 'To Do' or 'In Progress'.
Thanks
Lisa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for sharing the result of the tests.
Have a nice weekend!
Dario
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.