What impact do Linked Issues have on Completing a Sprint?

Steve_G
Contributor
October 6, 2023

When using the Link Issue feature, do specific Link types prevent a Sprint from being completed if all linked issues are not Done?

Use Case:

Multiple development Stories are completed in the current Sprint and appear in the right-most column of the Scrum Board. These Stories are linked to a single QA Test Story that will be completed in a future Sprint. When Completing the current Sprint, will we encounter an error because of the incomplete linked Stories? Does the link type (i.e. blocked by, relates to, is tested by) affect whether the Sprint can be Completed?

1 answer

1 accepted

1 vote
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 15, 2018

Hello,

You could create a filter like this:

updated > startOfDay(-1)

Then create a subscription for this filter to send the results of this filter once a day to a certain group of users. You can find more info about filter subscriptions here:

https://confluence.atlassian.com/jira064/receiving-search-results-via-email-720416706.html

Ashoutosh Pareek
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 18, 2018

Thank you very much

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 18, 2018

You are welcome!