we needs to write a automation

Angel
April 11, 2023

The Automation should be- when the dependent task is completed, then only my current task should be moved to dependent hold to On-track. 

 

Please tell me the automation procedure

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

3 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 6, 2018

This is a classic mistake by new administrators.

Never put the resolution on any screen other than a "transition" screen.

To fix this problem now, go to the project affected's configuration, find the issue type screen scheme and descend into it.  You should see it maps different issue types on to different screen schemes (there might only be one though).  Go into each screen scheme and look at each screen named in them, removing the resolution from Create or Edit screens (don't worry about view, Jira handles that for you)

Next, go to Admin -> Issues -> Screens and add a new screen, with just "resolution" on it.

Finally, go to the workflow, find the transition for "verify" and add the new resolution screen to it.

This will fix the problem, but still offer you Done, won't fix etc.  That can be fixed by the use of workflow properties, but get the resolution working correctly first.

0 votes
Answer accepted
Ollie Guan
Community Champion
June 6, 2018

Hi  @Chethana Hashani,

You need to set up multiple screen for the workflow

The screen should not contain the resolution fields when the Issue created