Is there a way (using Jira automation) to roll-up original estimates from Standard Issue Types to linked Epic?
I tried to use the formula {{#=}}{{issue.remaining estimate.sum}} / 60{{/}}
when issue equals Story and Value changes for Time Tracking
then for Epic update custom filed = {{#=}}{{issue.remaining estimate.sum}} / 60{{/}}
but it does not work.
What does atlassian-jira.log say ? I expect that will contain some errors telling you why it's not proceeding.