January 7, 2019

what field is required (from the drop down) to trigger the burndown for remaining hours? 

I have searched and can't figure it out....yes sure story points (SP) shows but that doesn't help bc SP are only closed once the epics are done.

 

Thank you

2 answers

0 votes
Rebecca Podmore
August 15, 2012

Something like this?

project = NR AND issue in linkedIssues(NR-1963, NR-1909, NR-1907,NR-1901,NR-845,NR-841,NR-840,NR-838,NR-820, "discovered while testing")

It doesn't work, it wants only one issue (the first), as per the error, can anyone help?

Issue link type 'NR-1909' could not be found in function 'linkedIssues'.

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 15, 2012

Unfortunately, that is all what JIRA supports at the moment. There third party plugins like JQL Tricks plugin that supports it but they are unavailable in JIRA onDemand.