I need to understand what % of our issues are getting deployed without moving through our QA process. Ideally, an issue status goes from In Progress to QA Ready to QA Started to QA Complete before being changed to Merged and then Deployed. Issues that bypass our QA Process will go straight from In Progress to Merged and then Deployed.
What would the syntax be for identifying recently resolved issues (say, in the last month) that moved through our QA statuses?
Rank is different from the Priority field. They are not connected. Rank is a global field across all projects, that is why issues from different projects can still be ranked. Priority is just a field. It is not connected to ranking.
Thanks Alex, I will work some more.
Rank is based on the User story ranking, correct? If so, how does one rank across projects? Also, with several tasks having the same priority - how are they ranked?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Rank is different from the Priority field. They are not connected. Rank is a global field across all projects, that is why issues from different projects can still be ranked. Priority is just a field. It is not connected to ranking.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can pull tasks up and down in the backlog and sprints. That is how you rank your tasks.
Or you can use the Priority field.