I am using scrum board and when I open my backlog I see story points sum for the sprint but not for the backlog.
How do I enable this feature?
Hello,
It is a next-gen project. You can not assign a new permission scheme for next-gen projects. You should create a classic project.
Is there any way to change the project type from Next-Gen to Classic?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No, you need to create a new project and then "bulk move*" the user stories to the classic project.
* - Bulk move also not possible in next-gen projects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is exactly what i was trying to do... been searching everywhere why i can not find the option. :(
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Only for classical projects. Next gen user restrictions would be entirely different then.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.