Hello everyone!
I have created a new board in Work Management, created Epics and new features underneath it, but I'm having struggles with 3 issues:
1. Is there a way to move an Epic from one column to another and have all the sub tasks underneath it move as well?
2. How can I present the Epics on the board but having the option to expand the epic and present the subtasks underneath it and not separately from the Epic?
3. Is there a way (maybe creating a rule) of changing one of the objects (Epic or subtask) priority and the parent/child to be changed accordingly?
Thanks a million!
Hagit
Hi Anirban,
From the description you have provided, it appears that what you refer to as "Master User Stories", should be an Epic.
Each Scrum team can create their stories within their boards, with the Epic Link field set to the Epic.
Some guidance for the scenario you have described.
Each Scrum team will have their own backlog, Sprint Board, Sprint Cycle - Multiple Scrum Board and multiple Sprint-1/2/3 etc.. for different Scrum teams within same Project
Create a separate Jira project to track Epics. If a higher level than Epic is required, create a new Issue Type called Initiative, and use Portfolio for Jira to vizualize Initiatives, Epics and the linked stories from multiple teams. Create a separate Jira project per Scrum team where they track associated Stories to the Epic using the Epic Link field. They can also create Bugs, Tasks and any other issue types relevant to their own teams.
2. Link the Tech stories within each Scrum to the Master User Stories and get the point-in-time view of the Master User stories at Project level
Portfolio for Jira addresses this use case. Take a look at the documentation at
https://confluence.atlassian.com/jiraportfolioserver/tracking-progress-and-status-814212695.html
https://confluence.atlassian.com/jiraportfolioserver/using-the-scope-view-802170536.html
3. Generate Reports/metrics (Velocity, Burn down Chart at Scrum team level as well as Project level
You can create a separate board that includes all the Epics and Stories to view Velocity and Burndown across multiple teams. Alternatively, EazyBI, Arsenale DataPlane, and other add-ons provide more reporting functionality. I have provided a couple of examples below.
https://docs.eazybi.com/display/EAZYBIJIRA/Sprint+burn-down+or+burn-up+chart
http://www.arsenalesystems.com/docs/display/dataplane/Rolling+Up+Epic+Time+Estimates
If you are looking for further guidance on best practices, I suggest working with our Solution Partner network. Let me know if you require more info on this.
Hope that helps.