Automation: Due date has to change for all stories of Epic if any story due date changes

Shivaprasad Hattaraki
November 19, 2023

Hello,

I want to change the due date of all stories under epic if any of the story due date changes.

 

Scenario: I have Epic-1, Story-1, Story-2, Story-3, Story-4

If the Story-2 due date changes, automatically Story-1, Story-3 and Story-4 due date has to be updated with the Story-2 due date Plus 3 days.

But the Story-2 due date should not be updated with value plus 3 days.

 

1 answer

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 15, 2018

Hi Ghanshyam,

Currently, it's not possible to export a single project on Jira Cloud.
We have a feature request suggesting the implementation of this ability:
- https://jira.atlassian.com/browse/JRACLOUD-34307
Please, click on vote and watch to receive updates about the feature.

For now, you must filter the tickets from this project and export as XML, RSS, Word or CSV and import on Azure Cloud if it has support to import these types of file.

Regards,
Angélica